| BLDG FINAL CERT OF COMP | | | | |
|
| SLAB | | | | |
|
| PLUMBING SLAB | DARIN OXENTINE | | | |
|
| PLUMBING ROUGH | DARIN OXENTINE | | | |
|
| PLUMBING ABOVE CEILING | DARIN OXENTINE | | | 7/22/2020 11:54:53 AM
bathrooms ok.
|
|
| PLUMBING FINAL CERT OF COMP | DARIN OXENTINE | | | |
|
| ELECTRICAL FINAL CERT OF COMP | | | | |
|
02/28/2020 | FOOTING | DARIN OXENTINE | PARTIAL | | 2/28/2020 11:01:55 AM
footings ok per plan and also being 3rd party inspected.
|
|
| FOOTING | | | | |
|
02/28/2020 | LOCATION SETBACKS | DARIN OXENTINE | APPROVED | | |
|
03/03/2020 | FOOTING | DARIN OXENTINE | PARTIAL | | 3/3/2020 1:07:33 PM
ok per plans also 3rd party inspected.
|
|
| FOOTING | | | | |
|
03/06/2020 | FOOTING | DARIN OXENTINE | PARTIAL | | 3/6/2020 1:21:26 PM
west side of building also 3rd party inspected
|
|
| FOOTING | | | | |
|
03/10/2020 | SEWER | DARIN OXENTINE | APPROVED | | |
|
03/11/2020 | ELECTRICAL SLAB | DARIN OXENTINE | PARTIAL | | 3/11/2020 12:19:07 PM
steel bond ok.
|
|
03/11/2020 | FOOTING | DARIN OXENTINE | PARTIAL | | 3/11/2020 1:22:16 PM
footing for firewall and pier front west corner of addition.
|
|
| FOOTING | | | | |
|
03/12/2020 | FOOTING | DARIN OXENTINE | APPROVED | | 3/12/2020 2:55:28 PM
rebar inspection ok per plan all footings are being 3rd party inspected.
|
|
03/12/2020 | WATER SUPPLY | DARIN OXENTINE | PARTIAL | am pleasdomestic water line for building | 3/12/2020 2:57:07 PM
water line around the perimeter of building ok.
|
|
03/12/2020 | FOUNDATION | DARIN OXENTINE | PARTIAL | | 3/12/2020 2:58:17 PM
east side of building
|
|
03/19/2020 | PLUMBING SLAB | DARIN OXENTINE | PARTIAL | | |
|
| PLUMBING SLAB | | | | |
|
03/20/2020 | FOUNDATION | DARIN OXENTINE | PARTIAL | | 3/20/2020 1:17:43 PM
rebar inspection back of building
|
|
| LOW VOLTAGE ROUGH | | | LEFLERS | |
|
03/24/2020 | FOUNDATION | DARIN OXENTINE | PARTIAL | | 3/24/2020 10:54:14 AM
fire wall back of building
|
|
| FOUNDATION | DARIN OXENTINE | | | 3/24/2020 10:54:22 AM
fire wall back of building
3/25/2020 11:36:22 AM
fire wall back of building
|
|
| FOUNDATION | DARIN OXENTINE | | | 3/24/2020 10:54:22 AM
fire wall back of building
3/25/2020 11:36:22 AM
fire wall back of building
|
|
| FOUNDATION | DARIN OXENTINE | | | 3/24/2020 10:54:22 AM
fire wall back of building
3/25/2020 11:36:25 AM
fire wall back of building
|
|
03/25/2020 | FOUNDATION | DARIN OXENTINE | PARTIAL | | 3/24/2020 10:54:21 AM
fire wall back of building
|
|
| FOUNDATION | DARIN OXENTINE | | | 3/25/2020 11:36:28 AM
fire wall back of building
|
|
03/25/2020 | FOUNDATION | DARIN OXENTINE | PARTIAL | | |
|
03/26/2020 | FOUNDATION | RICK CLINE | INCOMPLETE | | 3/26/2020 2:11:19 PM
cancelled due to rain
|
|
| FOUNDATION | | | | |
|
03/30/2020 | FOUNDATION | RICK CLINE | PARTIAL | | 3/30/2020 2:59:38 PM
fire wall
|
|
| FOUNDATION | | | | |
|
03/31/2020 | PLUMBING SLAB | RICK CLINE | PARTIAL | | 3/31/2020 2:02:35 PM
gang rest rooms only
|
|
04/06/2020 | PLUMBING SLAB | RICK CLINE | APPROVED | | |
|
04/07/2020 | WATER SUPPLY | RICK CLINE | APPROVED | early asap. domestic waterline | |
|
04/08/2020 | PLUMBING SLAB | RICK CLINE | APPROVED | roof drains | |
|
04/09/2020 | SLAB | RICK CLINE | APPROVED | | |
|
04/22/2020 | ELEC UNDERGROUND | DARIN OXENTINE | PARTIAL | | 4/22/2020 8:57:52 AM
underground to transformer.
|
|
05/27/2020 | ELECTRICAL ROUGH | RICK CLINE | REJECTED | | 5/27/2020 1:15:36 PM
should be saw service
|
|
05/27/2020 | FRAMING | RICK CLINE | PARTIAL | | 5/27/2020 1:16:13 PM
exterior walls
|
|
01/31/2020 | SAW SERVICE | DARIN OXENTINE | APPROVED | VOIDED (LAM 5/27/2020) | 1/30/2020 10:26:19 AM
1/30/2020 10:26 AM William Malone
Contact Name: joe guzzi
Site Address: 1206 MUSEUM RD
Phone: 7042307258
e-Mail: tmatzke@southfairelectric.com
5/27/2020 1:28:43 PM
Inspection voided by LAM. Most recent remarks follow: eTRAKiT Inspection Request
5/27/2020 1:33:04 PM
5/27/20 inspection should have been for the construction trailer (#304726)
|
|
05/28/2020 | SAW SERVICE | DARIN OXENTINE | REJECTED | | 5/27/2020 1:34:38 PM
for building
5/28/2020 12:42:43 PM
(add disconnect at pole and bond steel)
|
|
05/29/2020 | SAW SERVICE | DARIN OXENTINE | APPROVED | | 5/28/2020 12:42:51 PM
(add disconnect at pole and bond steel)
5/28/2020 12:42:51 PM
for building
|
|
05/29/2020 | ELECTRICAL ROUGH | DARIN OXENTINE | REJECTED | | |
|
06/03/2020 | FRAMING | DARIN OXENTINE | PARTIAL | | 12/4/2019 2:29:18 PM
Deferred Submittal (Fire Sprinklered Building) - do not result Framing Rough w/o approval of the Fire Marshal
6/3/2020 2:25:40 PM
(metal stud wall east side of building)
|
|
06/03/2020 | INSULATION | DARIN OXENTINE | PARTIAL | | 6/3/2020 2:25:46 PM
insulation behind steel i beams.
|
|
| INSULATION | DARIN OXENTINE | | | 6/3/2020 2:25:51 PM
insulation behind steel i beams.
|
|
06/08/2020 | FRAMING | DARIN OXENTINE | PARTIAL | | 6/3/2020 2:25:45 PM
(metal stud wall east side of building)
6/3/2020 2:25:45 PM
Deferred Submittal (Fire Sprinklered Building) - do not result Framing Rough w/o approval of the Fire Marshal
6/8/2020 3:11:06 PM
boxing around windows
|
|
06/23/2020 | SHEATHING AND FLASHING | DARIN OXENTINE | PARTIAL | | 6/23/2020 12:31:58 PM
back and right side of building
|
|
| SHEATHING AND FLASHING | DARIN OXENTINE | | | 6/23/2020 12:32:03 PM
back and right side of building
|
|
| SHEATHING AND FLASHING | DARIN OXENTINE | | | 6/23/2020 12:32:03 PM
back and right side of building
|
|
06/25/2020 | SHEATHING AND FLASHING | DARIN OXENTINE | PARTIAL | | 6/25/2020 12:09:59 PM
front right of building
|
|
| SHEATHING AND FLASHING | | | | |
|
07/08/2020 | INSULATION | DARIN OXENTINE | PARTIAL | | 7/8/2020 11:50:41 AM
sound proofing
|
|
| INSULATION | | | | |
|
07/08/2020 | FRAMING | DARIN OXENTINE | PARTIAL | | 7/8/2020 11:52:41 AM
framing for drop ceiling in center of building
|
|
07/15/2020 | PLUMBING ROUGH | DARIN OXENTINE | PARTIAL | | 7/15/2020 11:39:25 AM
water lines and 2 sink drain near front entrance and storm drains.
|
|
| PLUMBING ROUGH | | | | |
|
07/15/2020 | INSULATION | DARIN OXENTINE | INCOMPLETE | | 7/15/2020 11:40:04 AM
canceled
|
|
| INSULATION | | | | |
|
07/16/2020 | GAS PIPING ROUGH | DARIN OXENTINE | PARTIAL | | 7/16/2020 10:11:38 AM
under ground gas piping from meter to building.
|
|
| GAS PIPING ROUGH | | | | |
|
07/16/2020 | INSULATION | DARIN OXENTINE | PARTIAL | | 7/16/2020 10:12:34 AM
high ceiling
|
|
| INSULATION | | | | |
|
07/20/2020 | ELECTRICAL ROUGH | DARIN OXENTINE | PARTIAL | Classrooms and Hallway | |
|
| ELECTRICAL ROUGH | | | Classrooms and Hallway | |
|
07/20/2020 | INSULATION | DARIN OXENTINE | PARTIAL | | 7/20/2020 2:10:45 PM
classrooms main high ceiling area
|
|
| INSULATION | | | | |
|
07/22/2020 | PLUMBING ABOVE CEILING | DARIN OXENTINE | PARTIAL | | 7/22/2020 11:54:49 AM
bathrooms ok.
|
|
| PLUMBING ABOVE CEILING | DARIN OXENTINE | | | 7/22/2020 11:54:53 AM
bathrooms ok.
|
|
07/30/2020 | MECHANICAL ROUGH | DARIN OXENTINE | PARTIAL | Partial Duct Seal | 7/30/2020 3:18:34 PM
duct seal
|
|
07/31/2020 | PLUMBING ROUGH | DARIN OXENTINE | PARTIAL | | 7/31/2020 1:15:23 PM
water line insulation in the walls
|
|
| PLUMBING ROUGH | | | | |
|
07/31/2020 | ELECTRICAL ROUGH | DARIN OXENTINE | APPROVED | | 7/31/2020 1:15:53 PM
wall rough
|
|
08/03/2020 | INSULATION | DARIN OXENTINE | PARTIAL | | 8/3/2020 2:14:49 PM
front entrance
|
|
| INSULATION | | | | |
|
08/13/2020 | ELEC UNDERGROUND | DARIN OXENTINE | REJECTED | | 8/13/2020 3:48:25 PM
(wrong insection need temp power permit)
|
|
| ELEC UNDERGROUND | DARIN OXENTINE | | | 8/13/2020 3:48:30 PM
(wrong insection need temp power permit)
|
|
| ELEC UNDERGROUND | DARIN OXENTINE | | | 8/13/2020 3:48:31 PM
(wrong insection need temp power permit)
|
|
| ELEC UNDERGROUND | DARIN OXENTINE | | | 8/13/2020 3:48:31 PM
(wrong insection need temp power permit)
|
|
08/17/2020 | TEMPORARY POWER | DARIN OXENTINE | REJECTED | | 8/17/2020 3:29:38 PM
canceled
|
|
08/24/2020 | TEMPORARY POWER | DARIN OXENTINE | APPROVED | | |
|
09/14/2020 | ELEC ABOVE CEILING | MATTHEW GALLYON | APPROVED | For classrooms | |
|
09/14/2020 | FRAMING | MATTHEW GALLYON | PARTIAL | | 9/14/2020 10:20:33 AM
stage framing ok
|
|
| FRAMING | MATTHEW GALLYON | | | 9/14/2020 10:20:37 AM
stage framing ok
|
|
| FRAMING | MATTHEW GALLYON | | | 6/3/2020 2:25:45 PM
(metal stud wall east side of building)
6/3/2020 2:25:45 PM
Deferred Submittal (Fire Sprinklered Building) - do not result Framing Rough w/o approval of the Fire Marshal
6/8/2020 3:11:09 PM
(metal stud wall east side of building)
6/8/2020 3:11:09 PM
Deferred Submittal (Fire Sprinklered Building) - do not result Framing Rough w/o approval of the Fire Marshal
6/8/2020 3:11:09 PM
boxing around windows
9/14/2020 10:20:36 AM
stage framing ok
|
|
| FRAMING | MATTHEW GALLYON | | | 6/8/2020 3:11:10 PM
(metal stud wall east side of building)
6/8/2020 3:11:10 PM
Deferred Submittal (Fire Sprinklered Building) - do not result Framing Rough w/o approval of the Fire Marshal
6/8/2020 3:11:10 PM
boxing around windows
9/14/2020 10:20:37 AM
stage framing ok
|
|
| FRAMING | MATTHEW GALLYON | | | 9/14/2020 10:20:38 AM
stage framing ok
|
|
09/14/2020 | GAS PIPING FINAL | MATTHEW GALLYON | APPROVED | | |
|
09/14/2020 | MECHANICAL ABOVE CEILING | MATTHEW GALLYON | REJECTED | | 9/14/2020 10:20:41 AM
seal all duct insulation connections
|
|
09/14/2020 | MECHANICAL ROUGH | MATTHEW GALLYON | REJECTED | Duct Seal for Rooftop Duct | 9/14/2020 10:21:00 AM
seal roof top ducts completely
|
|
09/16/2020 | WATER SUPPLY | DARIN OXENTINE | APPROVED | | |
|
09/16/2020 | MECHANICAL ABOVE CEILING | DARIN OXENTINE | PARTIAL | | 9/14/2020 10:20:54 AM
seal all duct insulation connections
9/16/2020 1:45:52 PM
(classrooms)
|
|
09/16/2020 | MECHANICAL ROUGH | DARIN OXENTINE | PARTIAL | Duct Seal for Rooftop Duct | 9/14/2020 10:21:04 AM
seal roof top ducts completely
9/16/2020 1:45:56 PM
(duct seal on roof)
|
|
09/17/2020 | WATER SUPPLY | DARIN OXENTINE | APPROVED | tie in main to building | |
|
09/23/2020 | ELECTRICAL ROUGH | DARIN OXENTINE | PARTIAL | stage av booth electrical room & platfor | 9/22/2020 10:57:26 AM
stage av booth electrical room and platform access
|
|
| ELECTRICAL ROUGH | | | stage av booth electrical room & platfor | |
|
09/29/2020 | FRAMING | DARIN OXENTINE | PARTIAL | | 9/29/2020 12:41:06 PM
stage ok.
|
|
| FRAMING | | | | |
|
10/01/2020 | BUILDING ABOVE CEILING | DARIN OXENTINE | PARTIAL | classrooms and corridor | |
|
| BUILDING ABOVE CEILING | | | classrooms and corridor | |
|
10/02/2020 | MECHANICAL ROUGH | DARIN OXENTINE | PARTIAL | Duct Seal for Rooftop Duct | 9/16/2020 1:46:00 PM
(duct seal on roof)
9/16/2020 1:46:00 PM
seal roof top ducts completely
|
|
| MECHANICAL ROUGH | | | Duct Seal for Rooftop Duct | |
|
10/02/2020 | MECHANICAL ABOVE CEILING | DARIN OXENTINE | PARTIAL | | 9/16/2020 1:45:55 PM
(classrooms)
9/16/2020 1:45:55 PM
seal all duct insulation connections
|
|
| MECHANICAL ABOVE CEILING | | | | |
|
10/02/2020 | ELEC ABOVE CEILING | DARIN OXENTINE | PARTIAL | Main Bathrooms, hallway, kitchen, storag | |
|
| ELEC ABOVE CEILING | | | Main Bathrooms, hallway, kitchen, storag | |
|
10/21/2020 | MECHANICAL FINAL CERT OF COMP | DARIN OXENTINE | REJECTED | | 10/21/2020 3:24:22 PM
need roof access
|
|
10/21/2020 | PLUMBING FINAL CERT OF COMP | DARIN OXENTINE | REJECTED | | 10/21/2020 3:26:11 PM
seal fire wall penetrations and caulk around toilets.
|
|
| PLUMBING FINAL CERT OF COMP | | | | |
|
10/27/2020 | PLUMBING FINAL CERT OF COMP | DARIN OXENTINE | REJECTED | | 10/27/2020 2:13:36 PM
need floor drain primer in fire room
|
|
| PLUMBING FINAL CERT OF COMP | | | | |
|
11/02/2020 | MECHANICAL FINAL CERT OF COMP | DARIN OXENTINE | APPROVED | | |
|
11/03/2020 | PLUMBING FINAL CERT OF COMP | DARIN OXENTINE | APPROVED | | |
|
| FIRE FINAL CERT OF COMP | ED HODGES | APPROVED | | |
|
11/06/2020 | LOW VOLTAGE FINAL | DARIN OXENTINE | APPROVED | eTRAKiT Inspection Request | 11/4/2020 1:12:22 PM
11/4/2020 1:12 PM LEFLERS ELECTRONICS INC.
Contact Name: LEFLERS ELECTRONICS INC.
Site Address: 1206 MUSEUM RD
Phone: 7047841022
e-Mail: leicad2@leisystems.com
|
|
11/06/2020 | ELECTRICAL FINAL CERT OF COMP | DARIN OXENTINE | APPROVED | | |
|
| ZONING FINAL | ELAINE ANTHONY | APPROVED | | |
|
11/13/2020 | BLDG FINAL CERT OF COMP | DARIN OXENTINE | REJECTED | | 11/13/2020 1:51:33 PM
canceled
|
|
| BLDG FINAL CERT OF COMP | | | | |
|
11/19/2020 | BLDG FINAL CERT OF COMP | DARIN OXENTINE | APPROVED | | |
|
11/19/2020 | CERT OF OCCUPANCY | DARIN OXENTINE | APPROVED | | |
|
11/19/2020 | COMPLETE PERMIT** | DARIN OXENTINE | APPROVED | | |
|