05/05/2024
11:16 AM

Iredell County Inspections Department

 
Permit No. AP-301473 Permit Type   BUILDING COMMERCIAL Site Address   1206 MUSEUM RD
STATESVILLE, NC 28625
Applied   10/03/2019 Applicant   ADW ARCHITECTS
Approved   Owner   WESTERN AVENUE BAPTIST CHURCH
Issued   12/09/2019 Contractor   EDIFICE- INC.
Parent Permit No.   Description   17,431 Sq Ft addition for Western Avenue Baptist Church
  Notes  
 
  Date of Inspection Inspection Type Inspector Result Remarks Notes

BLDG FINAL CERT OF COMP

SLAB

PLUMBING SLABDARIN OXENTINE

PLUMBING ROUGHDARIN OXENTINE

PLUMBING ABOVE CEILINGDARIN OXENTINE7/22/2020 11:54:53 AM bathrooms ok.

PLUMBING FINAL CERT OF COMPDARIN OXENTINE

ELECTRICAL FINAL CERT OF COMP

 02/28/2020FOOTINGDARIN OXENTINEPARTIAL2/28/2020 11:01:55 AM footings ok per plan and also being 3rd party inspected.

FOOTING

 02/28/2020LOCATION SETBACKSDARIN OXENTINEAPPROVED

 03/03/2020FOOTINGDARIN OXENTINEPARTIAL3/3/2020 1:07:33 PM ok per plans also 3rd party inspected.

FOOTING

 03/06/2020FOOTINGDARIN OXENTINEPARTIAL3/6/2020 1:21:26 PM west side of building also 3rd party inspected

FOOTING

 03/10/2020SEWERDARIN OXENTINEAPPROVED

 03/11/2020ELECTRICAL SLABDARIN OXENTINEPARTIAL3/11/2020 12:19:07 PM steel bond ok.

 03/11/2020FOOTINGDARIN OXENTINEPARTIAL3/11/2020 1:22:16 PM footing for firewall and pier front west corner of addition.

FOOTING

 03/12/2020FOOTINGDARIN OXENTINEAPPROVED3/12/2020 2:55:28 PM rebar inspection ok per plan all footings are being 3rd party inspected.

 03/12/2020WATER SUPPLYDARIN OXENTINEPARTIALam pleasdomestic water line for building3/12/2020 2:57:07 PM water line around the perimeter of building ok.

 03/12/2020FOUNDATIONDARIN OXENTINEPARTIAL3/12/2020 2:58:17 PM east side of building

 03/19/2020PLUMBING SLABDARIN OXENTINEPARTIAL

PLUMBING SLAB

 03/20/2020FOUNDATIONDARIN OXENTINEPARTIAL3/20/2020 1:17:43 PM rebar inspection back of building

LOW VOLTAGE ROUGHLEFLERS

 03/24/2020FOUNDATIONDARIN OXENTINEPARTIAL3/24/2020 10:54:14 AM fire wall back of building

FOUNDATIONDARIN OXENTINE3/24/2020 10:54:22 AM fire wall back of building 3/25/2020 11:36:22 AM fire wall back of building

FOUNDATIONDARIN OXENTINE3/24/2020 10:54:22 AM fire wall back of building 3/25/2020 11:36:22 AM fire wall back of building

FOUNDATIONDARIN OXENTINE3/24/2020 10:54:22 AM fire wall back of building 3/25/2020 11:36:25 AM fire wall back of building

 03/25/2020FOUNDATIONDARIN OXENTINEPARTIAL3/24/2020 10:54:21 AM fire wall back of building

FOUNDATIONDARIN OXENTINE3/25/2020 11:36:28 AM fire wall back of building

 03/25/2020FOUNDATIONDARIN OXENTINEPARTIAL

 03/26/2020FOUNDATIONRICK CLINEINCOMPLETE3/26/2020 2:11:19 PM cancelled due to rain

FOUNDATION

 03/30/2020FOUNDATIONRICK CLINEPARTIAL3/30/2020 2:59:38 PM fire wall

FOUNDATION

 03/31/2020PLUMBING SLABRICK CLINEPARTIAL3/31/2020 2:02:35 PM gang rest rooms only

 04/06/2020PLUMBING SLABRICK CLINEAPPROVED

 04/07/2020WATER SUPPLYRICK CLINEAPPROVEDearly asap. domestic waterline

 04/08/2020PLUMBING SLABRICK CLINEAPPROVEDroof drains

 04/09/2020SLABRICK CLINEAPPROVED

 04/22/2020ELEC UNDERGROUNDDARIN OXENTINEPARTIAL4/22/2020 8:57:52 AM underground to transformer.

 05/27/2020ELECTRICAL ROUGHRICK CLINEREJECTED5/27/2020 1:15:36 PM should be saw service

 05/27/2020FRAMINGRICK CLINEPARTIAL5/27/2020 1:16:13 PM exterior walls

 01/31/2020SAW SERVICEDARIN OXENTINEAPPROVEDVOIDED (LAM 5/27/2020)1/30/2020 10:26:19 AM 1/30/2020 10:26 AM William Malone Contact Name: joe guzzi Site Address: 1206 MUSEUM RD Phone: 7042307258 e-Mail: tmatzke@southfairelectric.com 5/27/2020 1:28:43 PM Inspection voided by LAM. Most recent remarks follow: eTRAKiT Inspection Request 5/27/2020 1:33:04 PM 5/27/20 inspection should have been for the construction trailer (#304726)

 05/28/2020SAW SERVICEDARIN OXENTINEREJECTED5/27/2020 1:34:38 PM for building 5/28/2020 12:42:43 PM (add disconnect at pole and bond steel)

 05/29/2020SAW SERVICEDARIN OXENTINEAPPROVED5/28/2020 12:42:51 PM (add disconnect at pole and bond steel) 5/28/2020 12:42:51 PM for building

 05/29/2020ELECTRICAL ROUGHDARIN OXENTINEREJECTED

 06/03/2020FRAMINGDARIN OXENTINEPARTIAL12/4/2019 2:29:18 PM Deferred Submittal (Fire Sprinklered Building) - do not result Framing Rough w/o approval of the Fire Marshal 6/3/2020 2:25:40 PM (metal stud wall east side of building)

 06/03/2020INSULATIONDARIN OXENTINEPARTIAL6/3/2020 2:25:46 PM insulation behind steel i beams.

INSULATIONDARIN OXENTINE6/3/2020 2:25:51 PM insulation behind steel i beams.

 06/08/2020FRAMINGDARIN OXENTINEPARTIAL6/3/2020 2:25:45 PM (metal stud wall east side of building) 6/3/2020 2:25:45 PM Deferred Submittal (Fire Sprinklered Building) - do not result Framing Rough w/o approval of the Fire Marshal 6/8/2020 3:11:06 PM boxing around windows

 06/23/2020SHEATHING AND FLASHINGDARIN OXENTINEPARTIAL6/23/2020 12:31:58 PM back and right side of building

SHEATHING AND FLASHINGDARIN OXENTINE6/23/2020 12:32:03 PM back and right side of building

SHEATHING AND FLASHINGDARIN OXENTINE6/23/2020 12:32:03 PM back and right side of building

 06/25/2020SHEATHING AND FLASHINGDARIN OXENTINEPARTIAL6/25/2020 12:09:59 PM front right of building

SHEATHING AND FLASHING

 07/08/2020INSULATIONDARIN OXENTINEPARTIAL7/8/2020 11:50:41 AM sound proofing

INSULATION

 07/08/2020FRAMINGDARIN OXENTINEPARTIAL7/8/2020 11:52:41 AM framing for drop ceiling in center of building

 07/15/2020PLUMBING ROUGHDARIN OXENTINEPARTIAL7/15/2020 11:39:25 AM water lines and 2 sink drain near front entrance and storm drains.

PLUMBING ROUGH

 07/15/2020INSULATIONDARIN OXENTINEINCOMPLETE7/15/2020 11:40:04 AM canceled

INSULATION

 07/16/2020GAS PIPING ROUGHDARIN OXENTINEPARTIAL7/16/2020 10:11:38 AM under ground gas piping from meter to building.

GAS PIPING ROUGH

 07/16/2020INSULATIONDARIN OXENTINEPARTIAL7/16/2020 10:12:34 AM high ceiling

INSULATION

 07/20/2020ELECTRICAL ROUGHDARIN OXENTINEPARTIALClassrooms and Hallway

ELECTRICAL ROUGHClassrooms and Hallway

 07/20/2020INSULATIONDARIN OXENTINEPARTIAL7/20/2020 2:10:45 PM classrooms main high ceiling area

INSULATION

 07/22/2020PLUMBING ABOVE CEILINGDARIN OXENTINEPARTIAL7/22/2020 11:54:49 AM bathrooms ok.

PLUMBING ABOVE CEILINGDARIN OXENTINE7/22/2020 11:54:53 AM bathrooms ok.

 07/30/2020MECHANICAL ROUGHDARIN OXENTINEPARTIALPartial Duct Seal7/30/2020 3:18:34 PM duct seal

 07/31/2020PLUMBING ROUGHDARIN OXENTINEPARTIAL7/31/2020 1:15:23 PM water line insulation in the walls

PLUMBING ROUGH

 07/31/2020ELECTRICAL ROUGHDARIN OXENTINEAPPROVED7/31/2020 1:15:53 PM wall rough

 08/03/2020INSULATIONDARIN OXENTINEPARTIAL8/3/2020 2:14:49 PM front entrance

INSULATION

 08/13/2020ELEC UNDERGROUNDDARIN OXENTINEREJECTED8/13/2020 3:48:25 PM (wrong insection need temp power permit)

ELEC UNDERGROUNDDARIN OXENTINE8/13/2020 3:48:30 PM (wrong insection need temp power permit)

ELEC UNDERGROUNDDARIN OXENTINE8/13/2020 3:48:31 PM (wrong insection need temp power permit)

ELEC UNDERGROUNDDARIN OXENTINE8/13/2020 3:48:31 PM (wrong insection need temp power permit)

 08/17/2020TEMPORARY POWERDARIN OXENTINEREJECTED8/17/2020 3:29:38 PM canceled

 08/24/2020TEMPORARY POWERDARIN OXENTINEAPPROVED

 09/14/2020ELEC ABOVE CEILINGMATTHEW GALLYONAPPROVEDFor classrooms

 09/14/2020FRAMINGMATTHEW GALLYONPARTIAL9/14/2020 10:20:33 AM stage framing ok

FRAMINGMATTHEW GALLYON9/14/2020 10:20:37 AM stage framing ok

FRAMINGMATTHEW GALLYON6/3/2020 2:25:45 PM (metal stud wall east side of building) 6/3/2020 2:25:45 PM Deferred Submittal (Fire Sprinklered Building) - do not result Framing Rough w/o approval of the Fire Marshal 6/8/2020 3:11:09 PM (metal stud wall east side of building) 6/8/2020 3:11:09 PM Deferred Submittal (Fire Sprinklered Building) - do not result Framing Rough w/o approval of the Fire Marshal 6/8/2020 3:11:09 PM boxing around windows 9/14/2020 10:20:36 AM stage framing ok

FRAMINGMATTHEW GALLYON6/8/2020 3:11:10 PM (metal stud wall east side of building) 6/8/2020 3:11:10 PM Deferred Submittal (Fire Sprinklered Building) - do not result Framing Rough w/o approval of the Fire Marshal 6/8/2020 3:11:10 PM boxing around windows 9/14/2020 10:20:37 AM stage framing ok

FRAMINGMATTHEW GALLYON9/14/2020 10:20:38 AM stage framing ok

 09/14/2020GAS PIPING FINALMATTHEW GALLYONAPPROVED

 09/14/2020MECHANICAL ABOVE CEILINGMATTHEW GALLYONREJECTED9/14/2020 10:20:41 AM seal all duct insulation connections

 09/14/2020MECHANICAL ROUGHMATTHEW GALLYONREJECTEDDuct Seal for Rooftop Duct9/14/2020 10:21:00 AM seal roof top ducts completely

 09/16/2020WATER SUPPLYDARIN OXENTINEAPPROVED

 09/16/2020MECHANICAL ABOVE CEILINGDARIN OXENTINEPARTIAL9/14/2020 10:20:54 AM seal all duct insulation connections 9/16/2020 1:45:52 PM (classrooms)

 09/16/2020MECHANICAL ROUGHDARIN OXENTINEPARTIALDuct Seal for Rooftop Duct9/14/2020 10:21:04 AM seal roof top ducts completely 9/16/2020 1:45:56 PM (duct seal on roof)

 09/17/2020WATER SUPPLYDARIN OXENTINEAPPROVEDtie in main to building

 09/23/2020ELECTRICAL ROUGHDARIN OXENTINEPARTIALstage av booth electrical room & platfor9/22/2020 10:57:26 AM stage av booth electrical room and platform access

ELECTRICAL ROUGHstage av booth electrical room & platfor

 09/29/2020FRAMINGDARIN OXENTINEPARTIAL9/29/2020 12:41:06 PM stage ok.

FRAMING

 10/01/2020BUILDING ABOVE CEILINGDARIN OXENTINEPARTIALclassrooms and corridor

BUILDING ABOVE CEILINGclassrooms and corridor

 10/02/2020MECHANICAL ROUGHDARIN OXENTINEPARTIALDuct Seal for Rooftop Duct9/16/2020 1:46:00 PM (duct seal on roof) 9/16/2020 1:46:00 PM seal roof top ducts completely

MECHANICAL ROUGHDuct Seal for Rooftop Duct

 10/02/2020MECHANICAL ABOVE CEILINGDARIN OXENTINEPARTIAL9/16/2020 1:45:55 PM (classrooms) 9/16/2020 1:45:55 PM seal all duct insulation connections

MECHANICAL ABOVE CEILING

 10/02/2020ELEC ABOVE CEILINGDARIN OXENTINEPARTIALMain Bathrooms, hallway, kitchen, storag

ELEC ABOVE CEILINGMain Bathrooms, hallway, kitchen, storag

 10/21/2020MECHANICAL FINAL CERT OF COMPDARIN OXENTINEREJECTED10/21/2020 3:24:22 PM need roof access

 10/21/2020PLUMBING FINAL CERT OF COMPDARIN OXENTINEREJECTED10/21/2020 3:26:11 PM seal fire wall penetrations and caulk around toilets.

PLUMBING FINAL CERT OF COMP

 10/27/2020PLUMBING FINAL CERT OF COMPDARIN OXENTINEREJECTED10/27/2020 2:13:36 PM need floor drain primer in fire room

PLUMBING FINAL CERT OF COMP

 11/02/2020MECHANICAL FINAL CERT OF COMPDARIN OXENTINEAPPROVED

 11/03/2020PLUMBING FINAL CERT OF COMPDARIN OXENTINEAPPROVED

FIRE FINAL CERT OF COMPED HODGESAPPROVED

 11/06/2020LOW VOLTAGE FINALDARIN OXENTINEAPPROVEDeTRAKiT Inspection Request11/4/2020 1:12:22 PM 11/4/2020 1:12 PM LEFLERS ELECTRONICS INC. Contact Name: LEFLERS ELECTRONICS INC. Site Address: 1206 MUSEUM RD Phone: 7047841022 e-Mail: leicad2@leisystems.com

 11/06/2020ELECTRICAL FINAL CERT OF COMPDARIN OXENTINEAPPROVED

ZONING FINALELAINE ANTHONYAPPROVED

 11/13/2020BLDG FINAL CERT OF COMPDARIN OXENTINEREJECTED11/13/2020 1:51:33 PM canceled

BLDG FINAL CERT OF COMP

 11/19/2020BLDG FINAL CERT OF COMPDARIN OXENTINEAPPROVED

 11/19/2020CERT OF OCCUPANCYDARIN OXENTINEAPPROVED

 11/19/2020COMPLETE PERMIT**DARIN OXENTINEAPPROVED