| LOW VOLTAGE ROUGH | | | | |
|
02/18/2020 | SAW SERVICE | BRADLEY NICHOLSON | APPROVED | | |
|
| GRADING COM | RANDALL MOORE | | | |
|
| LOCATION SETBACKS | JACK HARWELL | | | |
|
| SHEATHING AND FLASHING | JACK HARWELL | | | |
|
| PLUMBING FINAL CERT OF COMP | | | | |
|
02/26/2020 | ELECTRICAL SLAB | JACK HARWELL | APPROVED | | |
|
02/26/2020 | ELEC UNDERGROUND | JACK HARWELL | PARTIAL | | 2/26/2020 12:04:53 PM
Needed slab inspection
|
|
| ELEC UNDERGROUND | JACK HARWELL | | | 2/26/2020 12:04:57 PM
Needed slab inspection
5/5/2020 12:58:01 PM
3 light pole bollards ok
|
|
02/27/2020 | FOOTING | JACK HARWELL | PARTIAL | ENGINEER LETTER ONSITE AND SCANNED IN | 2/27/2020 12:28:51 PM
Engineering on footing poured prior to inspection , in file
|
|
| FOOTING | | | ENGINEER LETTER ONSITE AND SCANNED IN | |
|
02/28/2020 | PLUMBING SLAB | DANA LAPISH | APPROVED | | |
|
03/06/2020 | SLAB | JACK HARWELL | APPROVED | PM PLEASE | |
|
03/06/2020 | FOUNDATION | JACK HARWELL | PARTIAL | PM | 3/6/2020 5:34:32 AM
Need to see top out and 3rd party engineer report
|
|
04/08/2020 | INSULATION | JACK HARWELL | APPROVED | | |
|
04/08/2020 | FRAMING | JACK HARWELL | PARTIAL | | 4/8/2020 10:32:32 AM
Pending engineer sign off of metal roof framing. Exterior walls are solid
masonry
|
|
04/09/2020 | WATER SUPPLY | BENTLEY PARLIER | APPROVED | | |
|
04/09/2020 | ELECTRICAL ROUGH | BENTLEY PARLIER | APPROVED | | |
|
04/15/2020 | PLUMBING ROUGH | DANA LAPISH | PARTIAL | | 4/15/2020 4:26:36 PM
need to see piping is protected going through metal plates
|
|
| PLUMBING ROUGH | DANA LAPISH | | | 4/15/2020 4:26:41 PM
need to see piping is protected going through metal plates
4/16/2020 12:36:17 PM
need to see piping is protected going through metal plates
|
|
04/16/2020 | PLUMBING ROUGH | DANA LAPISH | APPROVED | | 4/15/2020 4:26:40 PM
need to see piping is protected going through metal plates
|
|
04/16/2020 | SEWER | DANA LAPISH | APPROVED | | 4/16/2020 12:36:18 PM
connected at Bldg. run out back turns right stopping at curb area / Remaining piping to run through grass area behind QT / Need engineering reports for boring & piping design
|
|
04/16/2020 | WATER SUPPLY | DANA LAPISH | APPROVED | MAIN | |
|
| GAS PIPING FINAL | | | | |
|
04/17/2020 | GAS PIPING ROUGH | DANA LAPISH | APPROVED | | |
|
04/17/2020 | GAS PIPING ROUGH | DANA LAPISH | APPROVED | | |
|
| MECHANICAL ROUGH | | | | |
|
04/23/2020 | MECHANICAL ROUGH | JACK HARWELL | APPROVED | | 4/23/2020 2:55:00 PM
Paint mixing booth duct seal and vent ok, 4 roof units handling open ceilings
|
|
04/30/2020 | GAS PIPING FINAL | DANA LAPISH | APPROVED | | |
|
04/30/2020 | PLUMBING FINAL CERT OF COMP | DANA LAPISH | APPROVED | | |
|
04/30/2020 | TEMPORARY POWER | DANA LAPISH | APPROVED | | |
|
05/05/2020 | SEWER | DANA LAPISH | PARTIAL | Consultation | 4/16/2020 12:36:20 PM
connected at Bldg. run out back turns right stopping at curb area / Remaining piping to run through grass area behind QT / Need engineering reports for boring & piping design
5/5/2020 10:46:01 AM
Meet with Plumbing Contr. the boring of pipe placement & connection
|
|
| SEWER | | | Consultation | |
|
05/05/2020 | ELECTRICAL ROUGH | JACK HARWELL | APPROVED | | |
|
05/14/2020 | MECHANICAL FINAL CERT OF COMP | DANA LAPISH | APPROVED | | |
|
| FIRE FINAL CERT OF COMP | Geoffrey R Woolard | APPROVED | | 5/15/2020 10:11:07 AM
MARK TROUBLEFIELD INSPECTED - 05/15/2020
|
|
05/15/2020 | ELECTRICAL FINAL CERT OF COMP | DANA LAPISH | APPROVED | | |
|
| ZONING FINAL | HEATHER POSTON | APPROVED | per MGable | |
|
05/15/2020 | BLDG FINAL CERT OF COMP | DANA LAPISH | REJECTED | | 5/15/2020 4:50:09 PM
Pending all Mooresville inspections approved / sewer eng. design & report for boring & Framing Engineering reports for steel components & additional roof members added
|
|
| BACKFLOW | MARY A BOLIEK | APPROVED | | |
|
05/28/2020 | FOUNDATION | DANA LAPISH | APPROVED | PM | 5/29/2020 7:26:49 AM
All engineering in attachments
|
|
05/28/2020 | FRAMING | DANA LAPISH | APPROVED | | 4/8/2020 10:32:35 AM
Pending engineer sign off of metal roof framing. Exterior walls are solid
masonry
5/29/2020 7:26:52 AM
All engineering in attachments
|
|
05/28/2020 | LOW VOLTAGE FINAL | DANA LAPISH | APPROVED | | |
|
| UTILITY FINAL | Gary L Harkey | APPROVED | | |
|
06/03/2020 | BLDG FINAL CERT OF COMP | DANA LAPISH | APPROVED | | 5/15/2020 4:50:15 PM
Pending all Mooresville inspections approved / sewer eng. design & report for boring & Framing Engineering reports for steel components & additional roof members added
|
|
06/03/2020 | COMPLETE PERMIT** | DANA LAPISH | APPROVED | | |
|
06/03/2020 | CERT OF OCCUPANCY | DANA LAPISH | APPROVED | | |
|