| ELECTRICAL ROUGH | | | | |
|
10/29/2019 | SERVICE CHANGE | MATTHEW GALLYON | APPROVED | | |
|
10/29/2019 | ELECTRICAL FINAL CERT OF COMP | MATTHEW GALLYON | REJECTED | | 10/29/2019 4:08:38 PM
need to finish runniing power circuit
|
|
11/06/2019 | ELECTRICAL FINAL CERT OF COMP | MATTHEW GALLYON | REJECTED | | 10/29/2019 4:08:41 PM
need to finish runniing power circuit
11/6/2019 11:42:47 AM
no one home to check inside panel. outside disconnect has leftover screws close to terminals, and grounding and bonding incorrect, need pv packet with structural engineers letter
|
|
11/08/2019 | ELECTRICAL FINAL CERT OF COMP | MATTHEW GALLYON | REJECTED | | 11/6/2019 11:42:52 AM
need to finish runniing power circuit
11/6/2019 11:42:53 AM
no one home to check inside panel. outside disconnect has leftover screws close to terminals, and grounding and bonding incorrect, need pv packet with structural engineers letter
11/8/2019 11:20:18 AM
(cancelled by contractor)
|
|
| COMPLETE PERMIT** | | | | |
|
11/25/2019 | ELECTRICAL FINAL CERT OF COMP | MATTHEW GALLYON | REJECTED | grounding and bonding still incorrect in | 11/8/2019 11:20:22 AM
need to finish runniing power circuit
11/8/2019 11:20:23 AM
no one home to check inside panel. outside disconnect has leftover screws close to terminals, and grounding and bonding incorrect, need pv packet with structural engineers letter
11/8/2019 11:20:23 AM
(cancelled by contractor)
11/25/2019 11:38:59 AM
grounding and bonding still incorrect in disconnect
|
|
12/05/2019 | ELECTRICAL FINAL CERT OF COMP | MATTHEW GALLYON | APPROVED | grounding and bonding still incorrect in | |
|